This document presents a project timeline and list of significant project milestones/submittals associated with the Sylvan Residential Complex:
Brown Residence
- PCB Remediation Plan for the building Envelope Repair Project submitted to EPA 4/6/2011
- PCB Remediation Plan for the ADA Bathroom Upgrade Project submitted to EPA 5/6/2011
- Supporting information/response to EPA questions regarding the Envelope Repair Project submitted to EPA 5/17/2011
- EPA Comment Letter received for the ADA Bathroom Upgrade Project PCB Remediation Plan 6/6/2011
- PCB Remediation Activities Substantially Completed May 2011 through August 2011
- Brown Residence PCB Remediation Update and Addendum submitted to EPA 11/17/2011
- PCB Remediation Status Report (Building Envelope Repair Project) submitted to EPA 2/10/2012
- PCB Remediation Project Status Report (building envelope repair and ADA restroom projects) included as Attachment 1 of this letter
McNamara Residence
- PCB Remediation Plan for Building Envelope Repair and ADA Restroom Upgrade Project submitted to EPA 3/21/2012
- Supporting information/rresponse to EPA questions (telephone and email communications) May through June 2012
- PCB Remediation Activities Substantially Completed May 2012 through August 2012 (final verification wipe samples collected November 2012)
- PCB Remediation Status Report - included in Attachment 2 of this letter
Cashin Residence
- Inspection and Inventory of suspected PCB containing sealants August 2012
- PCB Remediatin Plan - included as Attachment 3 of the letter
NOTE: Analytical laboratory reports and data validation summaries have not been included because of size constraints.