Long-term Maintenance and Monitoring Report 2013

This report has been prepared to document the results from the 2013 long term monitoring activities conducted at the following buildings on the University of Massachusetts (UMass) Amherst Campus:

  • Webster House – The MMIP was submitted on January 5, 2012 in accordance with Condition 16 of the EPA’s PCB Decontamination and Disposal Approval under 40 CFR 761.61 (c) and 761.79 (h) dated July 4, 2011
  • Tobin Hall Deck – The Monitoring and Maintenance Implementation Plan (MMIP) was submitted on March 13, 2012 in accordance with Condition 8 of the United States Environmental Protection Agency’s (EPA) PCB Risk-Based Decontamination and Disposal Approval under 40 CFR 761.61 (c) and 761.79 (h) dated February 28, 2012; monitoring activities were also conducted at those areas described in the September 2012 PCB Remediation Plan Addendum
  • Southwest Concourse – The MMIP was submitted on December 29, 2010 in accordance with Condition 13 of the EPA’s Southwest Residential Area Concourse PCB Cleanup and Disposal Approval under 40 CFR 761.61 (a) and (c) and 761.79 (h) dated August 30, 2010; monitoring activities were also conducted at those areas described in the PCB Remediation Plan Amendment dated May 9, 2011
  • Field and Grayson Houses – The MMIP was submitted on April 24, 2012 as part of the PCB Remediation Plan/Close Out Document for Field and Grayson House by ATC Associates, Inc.
  • Dubois Library Elevator Lobbies – The MMIP was submitted on March 29, 2013 in accordance with Condition 12 of the EPA’s Dubois Library PCB Cleanup and Disposal Approval under 40 CFR 761.61(c), 761.62, and 761.79(h) dated April 8, 2010.