Long-Term Maintenance and Monitoring Report 2012

MONITORING ACTIVITIES – AUGUST 2012

Woodard & Curran performed the following monitoring activities between August 2 and 20, 2012:

  • Tobin Hall Deck – A visual inspection of the encapsulated concrete wall surface was performed and one verification wipe sample collected;
  • Webster House – A visual inspection of the encapsulated interior elevator lobby walls and the metal cladding/window frames on the northwest building elevation was performed and three verification wipe samples collected from the interior lobby walls;
  • Southwest Concourse – A visual inspection of encapsulated concrete building walls, retaining walls, and concrete within the pedestrian tunnel was conducted and 19 verification wipe samples collected from representative locations throughout the project area; and
  • Field and Grayson Houses – A visual inspection of encapsulated concrete parapet wall materials at the roofline of the buildings was performed.